Mine water treatment

Since 2004, JBA Bentley and JBA Bentley have have delivered a range of projects with the Coal Authority, tackling challenging engineering problems to deliver safe and innovative solutions that treat mine water and improve the surrounding environment.


Schemes vary in nature, from the construction of new treatment facilities, cascades, lagoons and
reed beds to structural repairs and refurbishment works.

Lynemourth Mine Water Treatment Scheme
Lynemourth Mine Water Treatment Scheme

Lynemourth Mine Water Treatment Scheme
Lynemourth Mine Water Treatment Scheme

Lynemourth Mine Water Treatment Scheme
Lynemourth Mine Water Treatment Scheme

1/2

Lynemouth

Project: Lynemouth Mine Water Treatment Scheme 

Location: Northumberland

Value: £4m

Client: Coal Authority

More: UK Water Projects case study

Pumping capacity needed increasing at Lynemouth to manage rising water levels.

 

We constructed new cascades, treatment lagoons, an ochre sludge drying bed and associated infrastructure. The scheme
presented a number of challenges, from managing buried structures and pockets of asbestos; to working near railway lines; to safely dealing with 100,000T of contaminated soils.

Kimblesworth Mine Water Treatment Scheme
Kimblesworth Mine Water Treatment Scheme

Kimblesworth Mine Water Treatment Scheme
Kimblesworth Mine Water Treatment Scheme

1/1

Kimblesworth

Project: Kimblesworth Mine Water Treatment Scheme 

Location: County Durham

Value: £980k

Client: Coal Authority

At the former Kimblesworth colliery we constructed a new treatment scheme with aeration cascade, reed beds, channels, pipework, and landscaping.


The earthworks were delivered right first time and four weeks ahead of programme by using a GPS dozer working from a CAD model. Furthermore, no topsoil was removed from site; all was reused as growing medium in the reed beds.

Craig Yr Aber Mine Water Treatment Scheme
Craig Yr Aber Mine Water Treatment Scheme

Craig Yr Aber Mine Water Treatment Scheme
Craig Yr Aber Mine Water Treatment Scheme

1/1

Craig Yr Aber

Project: Craig Yr Aber Mine Water Treatment Scheme

Location: Bridgend, Wales

Value: £1.1m

Client: Coal Authority

To treat mine water prior to discharge into the environment, we engineered a new passive mine water treatment scheme, comprising settlement ponds, wetlands and drying beds.


Innovative bales made of recycled tyres were used to construct the embankments. Covered in excavated material from site, these provided a structurally-sound, sustainable embankment solution in-keeping with its surroundings